Nadvirnyansky refinery, now JSC "Naftokhimik Prykarpattya", one of the oldest businesses refining industry not only Ukraine but also in Europe.
The factory was founded in the late XIX century. the individual, whose name can not install, so the mention of its existence in 1902 and is now the official date of reference history.
The plant was designed for the distillation of local oil fields, which were in v.Bytkiv, v.Pasichna, v.Kosmach.Postachalas oil to the factory in wooden barrels, as well as in tanks with Borislav Lviv region.
In 1927 the plant processed 450 tons of oil a year, working only in summer. It worked waste oil distillation unit periodic operation, which consisted of seven cubes. In such a setup receiving gas from the end of boiling 225 ° C, the illuminant kerosene to the end of boiling 350° C and fuel oil.
In the 30 years of last century, the factory several times bought and sold to foreign companies.
In 1936, the owner of the factory bought the refinery in the village PECHENIZHYN Kolomiya district. All equipment was transported in the building, installed two large cube with deflehmatoramy to get parafinovoho oil, a parafinovyy plant, which produced 40 tons of paraffin per month.
In the years 1937-1938 pereroblyav plant is 750 tons of oil a month.
In 1939, the power plant has reached 1,000 tons per month.
In September 1939, the plant became a public company Soviet Union.
In 1940, built a cube for the distillation of crude oil on 24m3 and the power plant has increased to 1150 tons of oil a month.
During the German occupation of the western regions of the plant was broken and not working. Valuable equipment parafinovoho shop and installation of waste oil distillation were evacuated to Germany. After the war, the factory was restored in late 1944, he had already pereroblyav 1150 tons of oil a month.  | The director of factory in 1944 years was appointed Yuliya Vasylivna Soldak. | In 1945, is still a cub for the distillation of oil and pot brought from the Stanislavsky refinery, which would increase processing to 1350 tons of oil a month.
In 1949, set in motion another cub on 44 HS with preheater. In such a plant worked until 1954.
In the 1954-1955 year the plant was reconstructed. Vat installation demolished and the technological atmosphere-setting trubchata in oil refining capacity of 200 tons of oil per day.
Due to the fact that the plant was unprofitable, several times submitted a decision on the closure: in 1947-1953, in 1955 and 1958.
Thanks to perseverance V. Soldak and collective enterprises, closure of the plant did not happen. 23 Feb., 1960 Stanislavsky radnarhosp approved a project to expand the task Nadvirna oil refinery.
In 1961, was put in place ELZU combined installation capacity of ABT-600 tons per year.
In 1961, earned a CHP capacity of 2.5 megawatts and the bitumen plant with capacity of 88 thousand tons of bitumen a year. In 1963, was put into operation a new parafinovyy shop.
In 1964, put in place the installation of thermal cracking, with a capacity of 400 thousand tons per year.  | In 1965 year the leader of factory was become by Mykola Lavrentijovich Notsek. | In 1967, put into operation unit for the production of electrode coke capacity of 300 thousand tons per year.
In 1968, gave the first production plant for the production of synthetic fatty acids, the capacity of 25 tonnes per year (on current time the noted products are not produced).
 | From 1969th to 1972 the director of factory worked Petro Ivanovich Koval'chak. | In 1969, launched the installation of inert gas.
Since 1970 earned a catalytic reforming unit number 1, with a capacity of 300 tys.tn.
In 1971, put into operation hazofakelne economy.
 | In 1972-1973 years a factory was managed by a director Volodymyr Grigorievich Nikolishin. |
In the period since 1972 are set higher requirements for quality. Such demands to increase production of gasoline octane number of A-72taA-76.  | From 1973 till 1980, the factory led George Kostantynovich Pryymachuk. | In 1973, the State Certification Commission awarded the seal of diesel fuel.
During 1971-1975 AD Plant did not give new and additional facilities, but due to renovation of existing facilities, efficient use of capacity, the intensification of production achieved a significant increase in the production and quality products.
In 1976 the team refineries produced more than 44% of the total production with the state quality.
As a result of technological improvements and the use of fund development equipped:- Precinct for the production of cultural goods stores, such as: pouring petrol and kerosene in bottles for household needs, and then
- Filling paraffin for household needs.
- Vprovadzhenoavtomatychnu liniyurozlyvannya and packing paraffin.
 | In 1980 year the director of factory was become by Lev Pavlovich Buniy. | Since 1983, the countdown begins his working unit ELZU-AT-3, with a capacity of 1 million tons of oil a year.
In 1985 he was put into operation a complex for the production of low acids.
In 1987, launched a set of facilities for sewage treatment m.Nadvirnoyi.
In 1993, pursuant to Presidential Decree of 15.06.1993r. № 210/93 "On the corporatization of enterprises and the provisions of the order of corporatization company, approved by the Government of 15/07/1999r. Number 508 was started to implement measures for the privatization of state enterprises "Nadvornyansky refinery. The decision of the State Committee for oil and gas from 12.03.1994 № 92 on the basis of the state enterprise was established OAO Naftokhimic "and registered in 22.03.1994 (registration number 368-AT) Board Nadvirnyanskoyi administration. Certificate of registration of securities, registration № 82/1/96, from 13.02.1996r., The Ministry of Finance zasvidchylovypusk of "Naftokhimic.
In 1994, work began complex catalytic reforming number 2, with a capacity of 300 tonnes per year. | In 1997 year the leader of enterprise is elect Eger Dmytro Oleksandrovich. | Since 1997, the station earned pouring oil into the tanker.
In 1997-1998 was implemented automated system for measuring levels of inventory and raw materials park. | Volodymyr Opanasovich Trotsenko in 1998 year of Rule of Society. |
Constructed and put into operation the gas station number 2 in the village Mykulychyn.  | In 1999 AGM was elected Chairman of the Board Igor Petrovich Palycya. | At that time, shareholders, the leadership of "Naftokhimic developed another plan for future development to improve production efficiency and to increase its size.
In 1999, put into operation an automatic system pinohasinnya.
In the 2000-year extension completed the installation of mechanical wastewater treatment.
In the 2000-year reconstructed setting komprymuvannya gas (torch facilities). | In 2003 year the General meetings of shareholders' are elect Oleksandr Ivanovich Lazorko. |
By 2006, enacted: - Tanks storage capacity of 120 thousand m3 of oil;
- Installation of gas separation;
- Pipeline "Dolyna-Nadvirna", length of 70km;
- Items loading liquefied gas.
 | In March, 2006 the General meetings of shareholders' assert Chairman of Rule of JSC "Naftokhimik of Prykarpattya" Shilyaeva Oleksandra Leonidovicha, which manages Society for present time. | During this period, a reconstruction of the overpass pouring light oil, put into effect the chemical wastewater treatment technology from German company "AWAS Heinz Ihne" entered the second phase of commodity-raw park at 100 thousand m3, which was built in the park raw hydro diesel fuel.
At today completed work on the reconstruction of technological unit AT-3, the works of construction of hidrochyschennya diesel fuel.
|